{"id":15882,"date":"2018-02-03T06:40:41","date_gmt":"2018-02-03T11:40:41","guid":{"rendered":"http:\/\/traceyarial.com\/blog\/?p=15882"},"modified":"2018-02-18T16:45:31","modified_gmt":"2018-02-18T21:45:31","slug":"social-housing-struggle","status":"publish","type":"post","link":"https:\/\/traceyarial.com\/blog\/en\/social-housing-struggle\/","title":{"rendered":"The struggle to create safe clean social housing in Quebec"},"content":{"rendered":"<p>Four years ago, Verdun borough mayor Jean-Fran\u00e7ois Parenteau agreed to build social housing on a municipally-owned lot on Gaetan Laberge instead of a larger project containing both condos and social housing.<\/p>\n<p>It isn&#8217;t built yet in part because the land in question has to be decontaminated before residential units can be built. Add that price, which is likely to be in the millions of dollars to the cost of the social housing buildings, whatever form they take, and you get a challenging fundraising goal.<\/p>\n<p>And that&#8217;s in addition to the many emotional and security barriers to building fully-subsidized apartments for vulnerable and impoverished people.<\/p>\n<p>No matter where they live, or what their income might be, people can occasionally experience personal crises due to addiction, mental health challenges, and uncontrolled anger. Unfortunately, it can be much harder to hide these kinds of crises in a public building, even when most of the residences within it are private. That means that neighbours find out about every incident, and assume that unusual situations occur more often than they do. The stigma makes it hard to build social housing into the fabric of communities.<\/p>\n<blockquote><p>People don\u2019t want those units too close to home,\u201d said a condo developer in response to a question about integrating social housing into his projects when I first looked into this issue four years ago. \u201cThey\u2019re afraid their property values will go down.\u201d<\/p><\/blockquote>\n<p>Boroughs don\u2019t like lower property values either, nor do they appreciate handling security and social problems that are difficult to hide in large impoverished neighbourhoods.\u00a0 Despite a 2005 City of Montreal policy that requires 15% of social housing and 15% of affordable housing in all new developments with more than 200 units, boroughs and cities can make exceptions. Often, they require cash payments towards parks and public spaces instead.<\/p>\n<p>The result is a waiting list of 25,000 people for social housing while there\u2019s a glut of condominiums for sale. That&#8217;s 3,000 more people on the waiting list than when I covered this issue four years ago. And things then were bad:<\/p>\n<blockquote><p>Quebec, New Brunswick, Nova Scotia and PEI each have more than a year of inventory to absorb,\u201d wrote Robert Kavcic, a senior economist with BMO Financial in June, 2014. \u201cIn most cases, those are decade highs that exceed even levels seen at the height of the Great Recession.\u201d<\/p><\/blockquote>\n<p>Maintaining pure social housing after it\u2019s built can also be a challenge; in that model, tenants pay only 25% of their income in rent, regardless of how little they earn. Today, the social housing banner also includes low-income apartments, cooperative housing projects and seniors&#8217; residences run by non-profit entities.<\/p>\n<p>Some non-profit housing options exist, but most of today\u2019s pure social housing units were created with federal and provincial government financing in the sixties and seventies. In 1969, the federal government set up social housing neighbourhoods across the country through the Canada Mortgage and Housing Corporation (CMHC).<\/p>\n<p>By 1982, people weren\u2019t as concerned about social housing as they had been earlier. The CMHC began selling all of its buildings to local non-profits, a process they completed in 1994.<\/p>\n<p>Some imaginative local politicians reacted to ensure that the units remained accessible to low-income people. In Pierrefonds for example, local politicians helped tenants turn a 750-unit building called Cloverdale into Canada\u2019s largest housing cooperative.<\/p>\n<p>As inspiring as that project was, other regions didn\u2019t duplicate it. LaSalle Heights was owned by the same person, but instead of following the coop creation model, it was sold to private for-profit interests in 1988. The Canada Housing and Mortgage Corporation battled the decision in court for years, but ultimately lost the right to keep the units reserved for low-income tenants. Instead, the CMHC set up grants for tenants and partnered with the owners to keep the complex open for another fifteen years. That agreement officially expires next year and locals worry that the site is targeted for major gentrification, especially since the 750 units are no longer tracked by any public agency.<\/p>\n<p>The only social housing that is tracked carefully is that managed within the provincial HLM program. The <em>Office municipal d\u2019habitation de Montr\u00e9al<\/em> (OMHM) operates 20,810 low-rent apartments within this program, while the <em>Office municipal d\u2019habitation de Laval<\/em> (OMHL) operates another 1,120.<\/p>\n<p>Unfortunately, almost all of the apartment buildings in the program were built in the seventies, so they require annual maintenance and occasional renewal projects that creates inconveniences for everyone and give the program a bad name. Renovations, when they occur, cost millions of dollars.<\/p>\n<p>Hundreds of residents of a building on Plamondon, for instance, only just moved back into their units last June after three-and-a-half years and $10 million dollars in renovations that included removing mold.<\/p>\n<p>Many other buildings need the same treatment. At the same time, Montreal faces a severe shortage of affordable family-sized rental units.<\/p>\n<p>Verdun&#8217;s project remains one to watch to see whether any social housing solution can be found.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Four years ago, Verdun borough mayor Jean-Fran\u00e7ois Parenteau agreed to build social housing on a municipally-owned lot on Gaetan Laberge instead of a larger project containing both condos and social housing. It isn&#8217;t built yet in part because the land in question has to be decontaminated before residential units can be built. Add that price, [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":1149,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_wp_convertkit_post_meta":{"form":"-1","landing_page":"0","tag":"0","restrict_content":"0"},"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_hide_featured_image":false,"_jetpack_featured_image_duplicate_dismissed":0,"_jetpack_feature_clip_id":0,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_publicize_message":"","jetpack_publicize_feature_enabled":true,"jetpack_social_post_already_shared":true,"jetpack_social_options":{"image_generator_settings":{"template":"highway","default_image_id":0,"font":"","enabled":false},"version":2},"jetpack_post_was_ever_published":false},"categories":[21],"tags":[741,136,96,472,128],"class_list":["post-15882","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-island-report","tag-lasalle-2","tag-laval","tag-montreal","tag-social-housing-2","tag-verdun","post-wrapper","thrv_wrapper"],"jetpack_publicize_connections":[],"jetpack_sharing_enabled":true,"jetpack_shortlink":"https:\/\/wp.me\/p2buQs-48a","jetpack-related-posts":[{"id":18717,"url":"https:\/\/traceyarial.com\/blog\/en\/last-week-march-2018-verdun\/","url_meta":{"origin":15882,"position":0},"title":"This week in Verdun: land decontamination possible, garbage contract cancelled, another good restaurant","author":"Tracey Arial","date":"March 26, 2018","format":false,"excerpt":"Verdun was in the news many times during the last week of March\u00a02018. Our political representatives made announcements about a program to help decontaminate soil and the cancellation of a garbage collection contract. Le Pigor got its first review and Promenade Wellington's annual sugar shack festival finished with record\u00a0crowds. Gaetan\u2026","rel":"","context":"In &quot;Verdun&quot;","block_context":{"text":"Verdun","link":"https:\/\/traceyarial.com\/blog\/en\/category\/canada\/verdunposts\/"},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/traceyarial.com\/blog\/wp-content\/uploads\/IsabelleMelancon-1.png?fit=200%2C200&ssl=1&resize=350%2C200","width":350,"height":200},"classes":[]},{"id":3193,"url":"https:\/\/traceyarial.com\/blog\/en\/verdun-councillors-active-since-election\/","url_meta":{"origin":15882,"position":1},"title":"Verdun Councillors Active Since the Election","author":"Tracey Arial","date":"December 17, 2013","format":false,"excerpt":"The Borough of Verdun has already held two council meetings since the election, a special one on November 18 and the first regularly scheduled one on Tuesday, December 3. Also last week, several Verdun councillors were appointed by Denis Coderre to sit on Montreal\u2019s executive committee, the agglomeration council, and\u2026","rel":"","context":"In &quot;Politics That Matter&quot;","block_context":{"text":"Politics That Matter","link":"https:\/\/traceyarial.com\/blog\/en\/category\/cultural-identity\/politics-that-matter\/"},"img":{"alt_text":"","src":"","width":0,"height":0},"classes":[]},{"id":15629,"url":"https:\/\/traceyarial.com\/blog\/en\/lorraine-pintal\/","url_meta":{"origin":15882,"position":2},"title":"Conversation with Lorraine Pintal","author":"Tracey Arial","date":"April 4, 2014","format":false,"excerpt":"Four weeks ago, Lorraine Pintal took a leave of absence to run for the Parti Quebecois\u00a0in Verdun for the 2014 Quebec provincial election. Until then, Pintal was the long-time artistic director of the Theatre du Nouveau Monde, a position she\u2019s held since 1992. Pintal doesn\u2019t live in the riding she\u2026","rel":"","context":"In &quot;Journalism&quot;","block_context":{"text":"Journalism","link":"https:\/\/traceyarial.com\/blog\/en\/category\/writing\/notable-nonfiction\/journalism\/"},"img":{"alt_text":"Lorraine_Pintal_Fond2014[1]","src":"https:\/\/i0.wp.com\/traceyarial.com\/blog\/wp-content\/uploads\/Lorraine_Pintal_Fond20141-300x200.jpg?resize=350%2C200","width":350,"height":200},"classes":[]},{"id":591,"url":"https:\/\/traceyarial.com\/blog\/en\/verdun-invites-comments-about-densification-in-wellington-de-leglise-sector\/","url_meta":{"origin":15882,"position":3},"title":"Verdun Invites Comments about Densification in Wellington de L\u2019Eglise Sector","author":"Tracey Arial","date":"June 20, 2012","format":false,"excerpt":"Verdun welcomes citizen comments and memorandums about densifying the Wellington de L\u2019Eglise Sector as part of its master plan today, Wednesday, June 20 at 7 p.m. in the Council Hall on the second floor, 4555 Verdun Street. \u201cI\u2019d encourage you to think outside the box,\u201d said council member Ann Guy,\u2026","rel":"","context":"In &quot;Verdun&quot;","block_context":{"text":"Verdun","link":"https:\/\/traceyarial.com\/blog\/en\/category\/canada\/verdunposts\/"},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/traceyarial.com\/blog\/wp-content\/uploads\/2012\/06\/homessmall.jpg?resize=350%2C200","width":350,"height":200},"classes":[]},{"id":2985,"url":"https:\/\/traceyarial.com\/blog\/en\/jean-francois-parenteau\/","url_meta":{"origin":15882,"position":4},"title":"Verdun Mayor Jean-Fran\u00e7ois Parenteau to Assist Executive Committee","author":"Tracey Arial","date":"November 19, 2013","format":false,"excerpt":"\u00a0 Denis Coderre named Jean-Fran\u00e7ois Parenteau, recently-elected\u00a0Mayor of Verdun, as an assistant member of Montreal\u2019s Executive Committee. He will concentrate on improving water infrastructure. Congratulations Mr. Parenteau. \u00a0 New Verdun Mayor: Jean-Fran\u00e7ois Parenteau Association: \u00c9quipe Denis Coderre pour Montr\u00e9al, http:\/\/www.equipedeniscoderre.com Jean-Fran\u00e7ois Parenteau will either inspire or scare you with his\u2026","rel":"","context":"In &quot;Verdun&quot;","block_context":{"text":"Verdun","link":"https:\/\/traceyarial.com\/blog\/en\/category\/canada\/verdunposts\/"},"img":{"alt_text":"Parenteau","src":"https:\/\/i0.wp.com\/traceyarial.com\/blog\/wp-content\/uploads\/Parenteau-288x300.png?resize=350%2C200","width":350,"height":200},"classes":[]},{"id":1231,"url":"https:\/\/traceyarial.com\/blog\/en\/verdun-legion-moving\/","url_meta":{"origin":15882,"position":5},"title":"Verdun Legion Moving","author":"Tracey Arial","date":"November 7, 2012","format":false,"excerpt":"Verdun Islamic Centre Sharing Space until December Last Sunday, November 4 was an emotional day for members of The Royal Canadian Legion\u2019s Branch 4 in Verdun. It was the last time that participants in the annual Verdun Remembrance Day parade could walk from the Cenotaph directly into the Great War\u2026","rel":"","context":"In &quot;Verdun&quot;","block_context":{"text":"Verdun","link":"https:\/\/traceyarial.com\/blog\/en\/category\/canada\/verdunposts\/"},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/traceyarial.com\/blog\/wp-content\/uploads\/VerdunLegion.jpg?resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/traceyarial.com\/blog\/wp-content\/uploads\/VerdunLegion.jpg?resize=350%2C200 1x, https:\/\/i0.wp.com\/traceyarial.com\/blog\/wp-content\/uploads\/VerdunLegion.jpg?resize=525%2C300 1.5x"},"classes":[]}],"jetpack_featured_media_url":"https:\/\/i0.wp.com\/traceyarial.com\/blog\/wp-content\/uploads\/760chuteAug2011.jpg?fit=300%2C225&ssl=1","_links":{"self":[{"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/posts\/15882","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/comments?post=15882"}],"version-history":[{"count":3,"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/posts\/15882\/revisions"}],"predecessor-version":[{"id":18318,"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/posts\/15882\/revisions\/18318"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/media\/1149"}],"wp:attachment":[{"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/media?parent=15882"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/categories?post=15882"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/traceyarial.com\/blog\/wp-json\/wp\/v2\/tags?post=15882"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}